Below is our second free CAPM practice test, which includes 15 more challenging project management questions. Working through practice questions is the most effective way to prepare for this exam.
Time limit: 0
Quiz Summary
0 of 15 Questions completed
Questions:
Information
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading…
You must sign in or sign up to start the quiz.
You must first complete the following:
Results
Test complete. Results are being recorded.
Results
0 of 15 Questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 point(s), (0)
Earned Point(s): 0 of 0, (0)
0 Essay(s) Pending (Possible Point(s): 0)
Categories
- Not categorized 0%
-
Question 1 of 15
1. Question
You have just been assigned to a major retailer’s new shopping cart project. Your first task is to determine the readiness of the retailer’s organization for a scrum approach. After your investigation, what would you tell your manager?
CorrectIncorrect -
Question 2 of 15
2. Question
Which technique is not a helpful practice in creating cultural compatibility for an agile approach?
CorrectIncorrect -
Question 3 of 15
3. Question
Which of the following choices best represents how iteration-based agile work is planned and scheduled?
CorrectIncorrect -
Question 4 of 15
4. Question
Which of the following is not an advantage of an iteration-based approach to agile?
CorrectIncorrect -
Question 5 of 15
5. Question
You are working with your agile team to decompose the project’s scope. Which activities will you undertake to accomplish this?
CorrectIncorrect -
Question 6 of 15
6. Question
Which of the following represents the best means of determining the scope of an iteration-based agile project?
CorrectIncorrect -
Question 7 of 15
7. Question
As the scrum master for the new photo transfer project that requires you to transition from the predictive lifecycle environment used on your previous project to an adaptive one, you need to understand some of the challenges in adaptive project tracking and control. What is an example of a status artifact you will likely see on this new adaptive project?
CorrectIncorrect -
Question 8 of 15
8. Question
As the scrum master for the new photo transfer project, you just completed refining the backlog for your current sprint, and your team has begun implementing the planned work. Which project tracking tool would you likely not use for determining your team’s progress?
CorrectIncorrect -
Question 9 of 15
9. Question
Which of the following agile methods generally do not utilize time-boxed iterations?
CorrectIncorrect -
Question 10 of 15
10. Question
How does an agile team know when they successfully completed a deliverable?
CorrectIncorrect -
Question 11 of 15
11. Question
Which prioritization methods are not seen on an adaptive project?
CorrectIncorrect -
Question 12 of 15
12. Question
Which of the following represents the best definition of a portfolio?
CorrectIncorrect -
Question 13 of 15
13. Question
Which of the following is not considered a project?
CorrectIncorrect -
Question 14 of 15
14. Question
Frank was just provided with a project charter and was briefed by the sponsor that the project has predictive characteristics. Which of the following would match those of such a lifecycle?
CorrectIncorrect -
Question 15 of 15
15. Question
As the project manager, Mary was recently visited by a member of her team who wanted her to be aware of a price increase of an integrated circuit chip she was about to order, which is integral to their product. Mary thanks them and writes this information down. Where did Mary likely log this information?
CorrectIncorrect
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15